HUB 2 Completions and Handover
Engineering inputs, completion records, certification, workflow and handover.
HUB 2 Completions and Handover
Presentation · 14 slides · 930 KB
GoTechnology HUB 2 workflow, with engineering inputs including Sharecat.
KAGES Systems
Connect engineering information, completion tasks, certification and handover in a structured paperless workflow.
KAGES presents a 100% paperless approach to completion information. HUB 2 connects tagged engineering data with construction and commissioning records, helping the project team see the evidence and outstanding work for each stage of handover.
The delivery service and the information system work together. Commissioning & Completions explains the field and management work; this page explains the supporting information workflow.
Start with the engineering and tag information. Add the relevant construction and commissioning tasks, inspection records and certificates. Use the system view to connect completion status, outstanding work and readiness for the next handover.
The workflow connects certification, supporting documentation and handover stages. Define the platform, engineering inputs and implementation responsibilities at the start of the assignment.

Explore the HUB 2 workflow diagrams and interface examples below. The separate Completions Overview includes field-reporting examples and the HUB1 dossier report.
Enlarge Hierarchy of Controls supplied safety slideThe supplied safety-topic slide ranks elimination, substitution, engineering controls, administrative controls and PPE. It illustrates the source safety topic within the project’s approved control arrangements.
Enlarge Supplied pre-walkdown and project-information approachIntroduction of HUB-2 GoC, pre-walking subsystems, trending and gap analysis, improvements and implementation, assurance and traceability.
The action panel describes populating HUB-2 with project data for a test pilot; a multidiscipline field completion engineering team; field and GoC data to identify project wins and potential bottlenecks; KPI-based monitoring; lessons-learned and comprehensive risk registers; and continuing HOD and engineering-drawing monitoring.
Enlarge Supplied example of pre-walkdown and non-pre-walkdown statusThe example reports 28 subsystems progressed to MC1 sign-off: 6 completed with field-team pre-walkdowns and 22 without pre-walkdowns.
For the 6 pre-walkdown subsystems, 105 early punch items were identified and closed, with 0 Category A and 1 Category B items raised at MC1. The 22 non-pre-walkdown subsystems recorded 37 Category A and 88 Category B items raised at MC1, and 125 punch items not identified.
The supplied comparison shows average slippage to MC1 sign-off of 1.3 days with pre-walkdown and 11.8 days without pre-walkdown, and links 125 unidentified punch items to 11.8 days of lost production. These are values from this supplied example.
Enlarge Supplied Hub 2 progress, collaboration and handover themesThe panel describes automated certification and handover, reduced manual data entry, technical records, real-time progress visibility and decision support, collaboration through web and mobile access, and scalable project-information arrangements.
Implementation depends on the engineering information, system boundaries, record requirements and delivery arrangements. KAGES brings completions expertise into that setup and the subsequent readiness process.
Agree the implementation programme around engineering-data readiness, team responsibilities, training and the required handover milestones.
The critical path and the systems and sub-systems being readied through HUB 2 also inform behavioural and cultural training. Before construction and commissioning teams work on a specific system, specialists use current worksite information to prepare a relevant VR session and live briefing.
Virtual Behavioural Solutions (VBS) brings actual hazards into that preparation, helping multicultural crews develop a shared understanding of the work ahead.
Engineering inputs, completion records, certification, workflow and handover.
Presentation · 14 slides · 930 KB
GoTechnology HUB 2 workflow, with engineering inputs including Sharecat.
Safety, walkdowns, dossiers, punch lists and field-completion practice.
Presentation · 7 slides · 563 KB
Includes the HUB1 dossier and punch-list reporting example from 2025.