Technical Consulting & Owner’s Engineer Guidance

Independent owner-side judgement for the decisions that affect project value, delivery and readiness.

When to Involve KAGES

Use KAGES when the owner needs an independent view of a development plan, engineering decision, contractor performance or project risk. We connect the technical evidence to the decision the owner needs to make.

What KAGES Provides

  • Technical consulting and Owner’s Engineer guidance for government energy departments, including oil-and-gas engineering advice and technical support during IOC contract negotiations.
  • Owner’s representation and independent cold-eyes reviews.
  • Review of IOC and Tier-1 EPC execution, engineering evidence and contractor interfaces.
  • Cost-recovery, contract-value and compliance auditing within the appointment.
  • Risk identification, mitigation, accountability and follow-up.
  • Technical expert-witness support for an agreed dispute or investigation.
  • Review against applicable national, contractual and technical requirements, including API, ISO and ASME where relevant.
Illustrative: Engineers reviewing a technical drawing alongside digital equipment records on a tablet.
Reviewing engineering drawings and controlled equipment information.

Representing the owner’s interests

Our review focuses on whether the proposed work is fit for purpose and represents value for the owner. We examine assumptions, interfaces and the evidence behind contractor submissions, then communicate findings and priorities clearly.

Contractor and technical assurance

We bring relevant engineering, quality, construction and commissioning expertise to the review. The assignment identifies the applicable contractual and technical standards, the evidence to be examined and how issues will be escalated.

A practical approach to project risk

A useful risk register connects a risk with its consequences, controls, responsible people and follow-up actions. The example below shows how those decisions can be recorded and reviewed through the project lifecycle.

Selected entries from the supplied source workbook; original row identifiers distinguish repeated record numbers. The complete example retains all 155 entries and 44 fields.

Source row 6: 4. Organizational
Risk Description: Causes & Event or Circumstance
General to other Projects: SharePoint Project Files hard to follow and disjointed. Can lead to files being double handled or misplaced or not tracked, need DCC assistance rather than retrieving on own. (Not user friendly)
Consequences / Impact
All documents for Project require easy logical tracking and current difficult to track and hard to ensure are fully correct and completed. Wrong information be stored and latest edition not known, correspondance not correct, quality checks unknown
Probability Score (score 1-5)
5
Impact Score (score 1-5)
4
Risk Rating (Before mitigation)
20
Probability (after mitigation)
1
Severity (after mitigation)
1
Risk Rating (After mitigation)
1
Risk Owner (Action By)
Client Project Management
Risk Response Plan Outline
Understanding all the Phases & Stage Gates and organising files into the correct area will vastly increase the efficiency of the project and bring understanding of current status within a Project.
Risk Actions Description
PMO and Document Control to organise files in unison and ensure Traceability and easy to Track.
Action Status Open/Closed
Open
Source row 7: 2. Economical
Risk Description: Causes & Event or Circumstance
General to other Projects: Need to ensure Document Control has the correct training and qualifications to hold such a critical position.
Consequences / Impact
It has been witnessed consistantly that the person incharge of Document Control does not have sufficient training which severly impacts the Project performance. Regular problems include, latest up-dated system drawing not issued, duplicate areas of information storage, personnel files used for information, lack of organising transmittals and daily correspondance, not making files easily tracable.
Probability Score (score 1-5)
5
Impact Score (score 1-5)
3
Risk Rating (Before mitigation)
15
Probability (after mitigation)
1
Severity (after mitigation)
1
Risk Rating (After mitigation)
1
Risk Owner (Action By)
Client Project Management
Risk Response Plan Outline
Retrain current Document Control or Hire a Better Qualified Document Control
Risk Actions Description
Massive Impact on normal work activities and time taken away from doing the job when searching for information which should be readily available
Action Status Open/Closed
Open
Source row 8: 4. Organizational
Risk Description: Causes & Event or Circumstance
General to other Projects: PM not picking own Project Management Team at the start of a Project
Consequences / Impact
A Project Manager should choose their own team based on the abilities each member brings to the team. Using none approved / personally vetted personnel runs a high risk of Project failure
Probability Score (score 1-5)
4
Impact Score (score 1-5)
4
Risk Rating (Before mitigation)
16
Probability (after mitigation)
1
Severity (after mitigation)
1
Risk Rating (After mitigation)
1
Risk Owner (Action By)
Client Project Management
Risk Response Plan Outline
Vet all new people prior to starting on the project.
Risk Actions Description
Do not accept personnel from outside or other projects without correctly vetting them
Action Status Open/Closed
Open

Relevant Experience

Relevant Expertise

Deliverables and Useful Information

  • A prioritised findings and recommendations record.
  • A risk and action view with responsibilities and follow-up points.
  • Decision support on the agreed engineering, contractor or contract-value question.

Information to Prepare

  • Project objectives and the decision required.
  • Relevant engineering, commercial and contractor records.
  • Existing risk registers, audit findings and delivery reports.

Presentations and Examples

KAGES Capability Statement

Read the written company statement or view the companion presentation for an overview you can share within your organisation.

KAGES Capability Statement

Document · 2 PDF pages · 319 KB

Company capabilities and selected experience across the KAGES team.

KAGES Capability Presentation

Presentation · 9 slides · 254 KB

An introduction to KAGES services and the team’s professional experience.

Explore the Related Topic: KAGES Capability Statement

Let’s talk

Discuss Owner-Side Assurance

The appointment defines the responsibilities, access, applicable requirements and deliverables.